Hits and misses among latest 10 GW solar tender amendments

Share

Responding to developer feedback, the Solar Energy Corporation of India has again amended the details of its manufacturing-linked 10 GW solar PV tender.

V.S. Gangadhara Rao – director of the Ananyavijaya Consultancy and a solar consultant with experience in PV manufacturing – has given pv magazine his verdict on the changes.

Execution of PV power plants under the tender can now be completed in four phases, with 10% of the output agreed under PPA to be achieved within 24 months and then a further 30% annually by the end of years three to five.

Dr. Rao feels this is more realistic, as it offers developers the chance to use PV modules from a domestic manufacturing plant with a 600 MW annual production capacity in years three to five. As part of the tender, successful bidders need to have a domestic solar manufacturing capacity – with the government aiming to establish 3 GW of manufacturing output to accompany the 10 GW generation capacity sourced from the tender.

Production obligations still a concern

Under the amended scheme, a waiver on inter-state transmission system (ISTS) connectivity charges has been extended by two years. Solar projects commissioned up to March 31, 2024 – previously March 2022 – will be eligible for the waiver.

If commissioning is delayed beyond March 2024, developers will have to bear ISTS charges, in which case, such charges or a tariff reduction due to the delay in commissioning – whichever is higher – would be applicable.

The 36-month deadline for completion of the manufacturing aspect of any bid is also practical, says Dr. Rao. However, he feels production obligations, especially for capacity utilization, are still of some concern to potential bidders.

“Utilization of 80% of the installed capacity in the very first year – while the module and wafer cutting operations can achieve this target – will be difficult, especially for ingot and cell manufacturing with [a] targeted efficiency of cells,” said the consultant.

“Ingot manufacturing requires considerable ramp up time to achieve the consistency of crystal structures essential for targeted efficiency. Training of manpower – for the first time in India; absorbing the technology; optimizing the right sources of raw materials and bill of materials items, in terms of quality, prices and availability; and sourcing of spare parts during ramp up – both regular and breakdown – are some of the major challenges that need to be addressed during the ramp up. So, while capacity utilization will be 80% in the 12th month, the average for the first twelve months will be in the range of 50-70%.”

Tariff cap needs to be raised

Similarly, cell manufacturing requires time to achieve targeted efficiencies and capacities. The challenges are the same as for ingot manufacturing.

“Production obligations of 80% and 90% of the installed capacity indirectly mandate the developers to use modules from their manufacturing plants, even in adverse cost/market price scenarios. This needs to be looked into,” added Dr. Rao.

The consultant says, compared to power projects of one to two years’ duration, five-year projects are exposed to enhanced risks, especially those related to domestic and international policy.

Currency fluctuations, technology changes, trade restrictions – such as safeguarding and anti dumping duties; integrated goods and services tax; and tariffs on capital items, raw materials and bill of materials – and an absence of sites with sufficient solar irradiation, are among such concerns.

Dr. Rao warned there is still not enough leeway in capped tariffs likely for the tender to address such risks for developers.

This content is protected by copyright and may not be reused. If you want to cooperate with us and would like to reuse some of our content, please contact: editors@pv-magazine.com.

Popular content

Waaree Energies approves investment in 300 MW electrolyzer, 3.5 GWh lithium-ion battery cell units
23 December 2024 Waaree Energies' board of directors has approved investment in setting up a 300 MW electrolyzer manufacturing plant and a 3.5 GWh Lithium-ion battery...