Andhra Pradesh has ambitious plans to increase its renewable energy capacity 2.5 times to 18 GW by 2022 and then four times by 2029. However, there are gaps that need to be addressed, if the state is to achieve this.
At the Institute for Energy Economics and Financial Analysis (IEEFA), we believe that better planning, improving the financial management of distribution companies (discoms), and addressing the issue of policy uncertainty can assist in building investor confidence, including attracting more investment for the greater deployment of renewable energy projects in the state.
While discoms in Andhra Pradesh are the best performing in India, ranked No.1 best performing state as per the UDAY portal, they need to improve their operational and financial performance further to assist in increasing the share of renewable energy mix in their total portfolio.
There are also measures to further enhance reliability, and matching of demand and supply so that the grid is better able to integrate the increasing share of low cost but intermittent renewable energy.
Presently, aggregate technical and commercial (AT&C) loss is 10.28%, which is half the national average. This needs to be further reduced given it is still double the world’s average.
Grid modernisation, transmission infrastructure development, increased billing, and theft control are some additional measures to further minimise energy lost.
Reducing the gap between average cost of supply (ACS) and average revenue requirement (ARR) could improve the financial sustainability of the discoms.
IEEFA notes the state should undertake tariff reforms and make tariffs cost reflective. The state should reduce the burden of government subsidies and cross subsidies and provide subsidies to only the targeted beneficiaries.
Additional measures include the deployment of decentralized renewable energy and promoting schemes like solar irrigation pumps and solar rooftops, etc. This will also enable discoms to reduce their costs on generation and reduce the requirement for ongoing transmission infrastructure capacity expansions.
Another measure looks at renewable energy costs to factor grid firming costs along with generation costs. Given the intermittent nature of renewable energy, it increases the need for flexible sources of generation to help maintain grid stability. Various technologies that can provide this include pumped hydro storage, gas peaking plants, faster ramping, more flexible but lower utilisation of coal-fired power plants and battery storage, etc. A stronger price signal to incentivise, such generators, will help drive the roll-out of flexible power technologies.
Andhra Pradesh is in an advantageous position with installed capacity of gas and pumped hydro storage that can provide balancing power when renewable energy is not available. The state should adopt an all-inclusive portfolio of flexible power technologies comprising gas, pumped hydro storage, concentrated solar thermal and batteries, etc., along with demand side response management to incentivise consumers to respond to periods of peak demand by automatically curtailing unnecessary demand.
Andhra Pradesh must introduce time-of-day pricing to help manage peak demand and variability for renewable energy while providing a better deal for consumers.
The state could also minimise risk by facilitating land acquisition and grid availability, etc. For example, industrial solar parks dramatically reduce land acquisition and grid connection risks, both allowing national and international capital to flow, while lowering the cost of capital and hence the tariff required.
Certainty of policies is key. India has deployed large capacities of renewable energy by promoting competition and transparency through the world-leading reverse auction bidding mechanism. The state should not jeopardise the process by putting excessively aggressive caps and undermining investor confidence by unplanned policy changes. This increases developer risks and will see tariff tenders rise as a result, or if changes are made post investment, it risks replicating the non-performing assets debacle evident in the thermal power sector.
Andhra Pradesh should make both promoters and discoms accountable for their decisions. A contract should be legally binding and enforceable. It is important to establish stability of rules and enforceable contracts, with non-refundable deposits from tender winners to ensure delivery, while discoms need to honour their commitments, such as paying producers when due. If promoters or discoms are bailed out and not held accountable, the lessons of the past are not going to be learnt and are set to be repeated.
Andhra Pradesh should embrace technological change as an innovation to modernise, expand and diversify its electricity system. Increased reliance on domestic renewables builds energy security, whilst progressively locking in a new, sustainable low cost, deflationary electricity supply. The state should demonstrate the use of these new technologies on the ground through pilots, and learn by doing in local market conditions, progressively scaling up and avoiding adopting a boom-bust cycle approach by encouraging business certainty. This will bring down the real cost of servicing demand over time and provide a reliable and sustainable source of supply to its consumers.
This commentary is based on a presentation entitled ‘Serving Energy Demand through Renewables’, delivered by Vibhuti Garg, Energy Economist with IEEFA India at the Andhra Pradesh Energy Innovation Summit 2019 on February 5, 2019. The Summit’s objective was to identify innovations and best practices in the energy sector to set Andhra Pradesh firmly on the path of becoming the most liveable state in terms of energy for its citizens. Policy recommendations and three of the best cutting-edge innovations were submitted to the Honourable Chief Minister, Shri N. Chandrababu Naidu and to Sri Ajay Jain, Principle Secretary, Energy during the valedictory session at the conference.
Related Links:
- IEEFA India: Improving India’s electricity sector through time-of-day pricing
- IEEFA India: New record with renewable energy installations 40 times higher than thermal
- IEEFA India: Grid investment needs to match enormous growth in renewable energy investment
The views and opinions expressed in this article are the author’s own, and do not necessarily reflect those held by pv magazine.
This content is protected by copyright and may not be reused. If you want to cooperate with us and would like to reuse some of our content, please contact: editors@pv-magazine.com.
Besides the facts mentioned in the above article, AP has a coast line of 900+ kM , which is a potential source for off shore wind energy. The Policy for this form of energy is in its infancy yet with the initiatives and drive of the leader of the state, this potential when harnessed will bring about a sea change in the power atlas of AP.
Coast line has potential for wind power generation for 24 hours a day and 300 days a year. Technical know how from manufacturers is available. Wind Power Engineers already proficient in on shore can be honed to gain skills required for casting the foundation and erection of Wind turbine.
Another form of energy that can be looked upon is Tidel energy. Coastal area has witnessed 71 cyclones in the last 100 years. R & D in this area will help harness this form which along with Off shore wind eliminates land acquisition problems.