SJVN tenders BoS package for 100 MW solar in Gujarat

Share

SJVN Green Energy has tendered the balance of system (BoS) package for a 100 MW (AC) grid-connected solar plant in the Patan district of Gujarat.

The prospective contractor’s scope of work includes design, engineering, supply, construction, erection, testing, commissioning and three years of comprehensive operation and maintenance of the solar plant, excluding the supply of PV modules.

“PV modules shall be supplied to the BOS contractor by SJVN Green Energy,” reads the tender document.

EPC completion period is 425 days from the award of contract.

To be eligible, the bidder should have an average annual turnover of INR 52 crore in the last three financial years.

Bidding closes on May 18.

 

This content is protected by copyright and may not be reused. If you want to cooperate with us and would like to reuse some of our content, please contact: editors@pv-magazine.com.

Popular content

Waaree starts solar module production at its USA facility
20 December 2024 Waaree Solar Americas has started trial production of PV modules at its facility in Texas. The facility is set to fully commission its Phase-1 manufac...